BR18 climate requirements and the documentation your project needs

BR18 climate requirements changed on 1 July 2025, with differentiated limits and wider coverage for new construction and certain extensions. Covered projects must also assess the construction process separately. Confirm the applicable regulation version, building category and exemptions before selecting a limit or setting the project’s documentation requirements.

· Kvalitetssikring Danmark

At a glance

  • BR18 climate requirements distinguish the calculation duty from applicable limits.
  • Building type and project scope affect the assessment.
  • A4 and A5 have a separate construction-process limit for covered projects.
  • Records and calculation assumptions need to be traceable at completion.

Who should assess BR18 climate requirements

The client and project advisers should resolve BR18 climate requirements while design and procurement decisions remain open. Identify the competent calculation specialist and the parties supplying information. Contractors and subcontractors need to understand their agreed data deliveries without being expected to determine the whole building’s regulatory position themselves.

Begin with a brief scope note. Record the proposed work, relevant permit application date and building use. Check mixed uses and extensions explicitly. BR18 climate requirements cannot be selected from a single limit copied from another project. Keep the reasoning with the project documents so later design changes can be assessed against it.

BR18 climate requirements and exceptions

Read the current provisions and the version applicable to the building case. BR18 climate requirements introduced from July 2025 include more project types, but there are exceptions. For example, certain residential and holiday-home extensions below 250 m² of heated floor area are exempt from the calculation duty. Obtain a specific assessment before relying on an exception.

Do not describe every refurbishment as covered new construction. Equally, avoid treating an extension as a refurbishment merely because it connects to an existing building. Ask the responsible adviser to explain the category and record the decision. BR18 climate requirements depend on that classification, which should be clear before the team starts collecting the calculation inputs.

Keep the building and construction process separate

For covered projects, BR18 climate requirements include separate limits for the relevant building life-cycle modules and for A4/A5. The construction-process limit is 1.5 kg CO₂-equivalent per m² per year. A low result in one part does not automatically compensate for exceeding the other limit.

Ask the calculation specialist to show these results distinctly. When preparing project information for BR18 climate requirements, label whether the data concerns products, site activities or another life-cycle module. The A4/A5 guide addresses practical site records. This overview addresses applicability and the information structure for the wider assessment.

Agree the calculation inputs early

Create an information list with the specialist preparing the calculation. Ask which quantities, product references and assumptions are needed, who supplies them and when. Under BR18 climate requirements, the calculation and its supporting documentation need to correspond to the project as delivered, rather than only an early design option.

Give each input a useful reference. Record the product or activity, quantity, unit and source of the information. Identify revisions where design or procurement changes affect the calculation. BR18 climate requirements are easier to manage when the information owner knows why a particular record is needed and how it will be used.

Make procurement changes visible

A substitute product can affect several different project deliveries. Ask the relevant adviser to review the change before treating it as acceptable for the climate calculation. BR18 climate requirements are one part of that review; structural, fire and other technical requirements may need separate consideration by the appropriate competent parties.

Retain the original and revised information with the decision. If a quantity changes, identify the updated source rather than editing a final total without explanation. This allows the calculation specialist to follow changes relevant to BR18 climate requirements and avoids losing the connection between a procurement decision and the issued assessment.

Choose and document the data approach

Official guidance provides different documentation routes, including project-specific information and permitted standard values for relevant construction-process inputs. Ask the calculation specialist which approach applies. BR18 climate requirements do not imply that every supplier must independently produce a complete building calculation.

Record assumptions and missing information explicitly. If the specialist uses an allowed value, retain the relevant reference and explain its use in the calculation. Do not disguise an estimate as measured consumption. For BR18 climate requirements, a reader should be able to distinguish supplied facts, permitted assumptions and unresolved inputs without searching through the entire email history.

Review BR18 climate requirements before completion

Schedule a review while there is still time to resolve missing inputs. Check that quantities, selected products and site records correspond to the final project information. The applicable BR18 provisions require documentation of the calculation and assumptions at completion. Organise the delivery so the relevant reviewer can find both the result and its basis.

Use an index that distinguishes the issued calculation, input records and explanatory notes. Keep outstanding items visible. BR18 climate requirements should be addressed through a controlled delivery and review process. A polished summary page cannot replace missing inputs or establish that the calculations have been assessed by the appropriate competent person.

Effective date and ongoing review

The changes discussed here entered into force on 1 July 2025. Application to an individual project depends on the relevant rules and dates. Sources were checked on 9 October 2026. Recheck BR18 climate requirements when the scope, classification or regulatory version changes, and keep that assessment with the building case.

Frequently asked questions

Are the rules the same for every building?

No. BR18 climate requirements include differentiated limits, scope provisions and exceptions. Have the responsible adviser identify the relevant category rather than applying a figure selected from a general article.

Is site consumption the complete climate calculation?

No. Site information supports the relevant construction-process modules. The wider building assessment has other inputs and modules. Keep those deliveries separate and coordinate them with the calculation specialist.

Can a good building result offset a poor site result?

The construction-process limit is separate from the building-level limit for covered projects. Review both distinctly. Do not merge them into one headline figure when checking BR18 climate requirements.

Does a supplier’s environmental document guarantee compliance?

No. Product information can support the assessment, but project quantities, scope and calculation rules still matter. Ask the responsible specialist how the particular document is used and retain the reference.

General professional information. The individual project may require legal or technical assessment. The suggested workflows do not replace applicable requirements or competent specialist instructions.

Sources checked 9 October 2026. Technically reviewed by Kvalitetssikring Danmark ApS.

Read more in our knowledge base

New construction rules in Denmark and what your project should check

Review new construction rules in Denmark, effective dates and documentation. Check the main changes and clarify project responsibilities before work.

Read article

A contractor stop order on a Danish construction site

Understand a contractor stop order in Denmark, affected work and documentation. Check the authority process and organise follow-up before restarting.

Read article

Asbestos rules for Danish construction projects

Check asbestos rules in Denmark, company authorisation, training and documentation. Clarify the planned activity with a competent specialist before work.

Read article

Selective demolition in Denmark and the 250 square metre threshold

Understand selective demolition in Denmark, the 250 m² threshold and project roles. Check applicability, authorisation and planning before work starts.

Read article

The demolition plan and the client’s MRK responsibilities

Organise a demolition plan and clarify the client’s MRK role in Denmark. Review appointment, project information and updates before covered work begins.

Read article

A4/A5 documentation for the construction process

Organise A4/A5 documentation for transport, energy and material waste. Agree records, units and reporting responsibilities with the calculation specialist.

Read article

Agree the project’s separate documentation tasks

Assign climate assessment to the competent specialist. Discuss structural execution documentation separately with KS Danmark where relevant. Coordinate the information shared between these tasks without presenting one as a substitute for the other.