The demolition plan and the client’s MRK responsibilities

A demolition plan for covered selective demolition needs a clear connection between the client, the environmental and resource coordinator and the performing company. The MRK helps ensure the standardised plan is prepared, submitted and followed. Appoint the role early, provide the relevant project information and keep plan changes traceable throughout the work.

· Kvalitetssikring Danmark

At a glance

  • A demolition plan belongs in the planning stage, before dismantling begins.
  • The client appoints the required MRK for covered selective demolition.
  • MRK coordination and the company’s resource-responsible role are distinct functions.
  • Updating the plan should include communicating the change to affected people.

Who needs an MRK

For covered demolition where at least 250 m² of floor area is completely removed, the client needs an environmental and resource coordinator. Confirm applicability and transition with the relevant specialist. The demolition plan must reflect the project assessed, rather than an assumed area or a description copied from a previous building.

MRK stands for miljø- og ressourcekoordinator. The role is advisory and coordinating on the client’s side. A demolition plan also relies on information and action from the demolition company, consultants and other project parties. An appointment works best when those interfaces are agreed, so the coordinator can obtain information and follow up on actual work.

Appoint the coordinator before planning is complete

Appoint the MRK before filling out the standardised demolition plan. The agency’s guidance also specifies appointment no later than three weeks before demolition begins. Check the coordinator’s required qualifications and allow enough time for the actual planning task. A name entered on a form is not the same as a functioning appointment.

Set out the agreed tasks, available information and communication arrangements. Identify who provides surveys, drawings and procurement details. Explain how the MRK raises an unresolved question about the demolition plan and who makes decisions requiring the client’s involvement. Keep these arrangements accessible to the project team rather than leaving them only in a consultant’s appointment letter.

Provide useful information

Give the coordinator the current description of the work and relevant findings about the building. Distinguish verified information from assumptions and outstanding investigations. A demolition plan should not conceal uncertainty by using a confident description of material that has not yet been adequately assessed.

Use a clear information list. For each missing item, record who will obtain it and when the project needs it. An updated drawing, an environmental finding or a change of performing company can affect the demolition plan. Ask the coordinator to identify which changes need assessment and which documents should be revised before the relevant phase proceeds.

Separate the project roles

The MRK’s coordination function and the authorised company’s resource-responsible function are different. One appropriately qualified person can potentially perform both, but the appointments and responsibilities still need clarity. A demolition plan should make it possible to see which function a person is carrying out when making a decision or recording a follow-up.

Ask the performing company who handles its supervision and employee instructions. Ask the client’s coordinator how progress against the demolition plan will be followed. Agree how the two exchange information. This avoids a situation where each party believes the other has checked a change, while neither has documented an assessment.

Keep the issued demolition plan under control

Give every issued demolition plan a version, date and identifiable owner. Keep earlier versions as history according to the project procedure. Make the current working version easy to find, including for supervisors who join the project later. A filename containing “final” is not a sufficient explanation of the document’s status.

When a change is needed, record the reason and affected activity. Identify who reviewed the update and how it was communicated. The demolition plan should show the current arrangements without erasing the basis for earlier actions. Link relevant observations and correspondence so a reviewer can follow why the plan changed.

Use follow-up that helps the site team

The MRK follows whether the plan’s elements are being implemented. Agree a practical way to record observations and actions. An action relating to the demolition plan should identify the location, condition, required clarification and owner. A general comment that “documentation is missing” rarely tells the team what to do next.

Discuss the upcoming sequence as well as completed work. Check whether planned material separation and information are ready for the next activity. Where the demolition plan relies on an unresolved assumption, make that dependency clear. Obtain the appropriate competent decision before using a general programme deadline as the reason to proceed.

Demolition plan records for handover

Agree which records the client will receive and how they relate to the demolition plan. Relevant project records may include issued versions, submissions, assessments, follow-up actions and material information. Confirm the actual obligations and delivery scope rather than treating this suggested index as a complete legal checklist.

Review the records in stages. Check that the latest demolition plan corresponds to the final account of the work and that changes are explained. Keep open items visible with an owner and next step. Handover is easier when it brings together records maintained during the work instead of requiring the team to reconstruct decisions from emails afterward.

Effective date and review date

The selective demolition requirements discussed here were introduced from 1 July 2025, subject to the project’s transitional position. Sources were checked on 9 October 2026. Check the current requirements and guidance before issuing a demolition plan, especially where project scope or appointment arrangements have changed.

Frequently asked questions

Can the demolition company provide the MRK?

The agency allows this arrangement, but the client’s appointment and responsibilities still need to be clear. Confirm qualifications, access to information and follow-up arrangements for the demolition plan. Do not assume the company’s authorisation automatically includes the client-side appointment.

Can the same person hold both roles?

That can be possible where the person meets the relevant qualification requirements. Keep the two functions explicit in the appointments and demolition plan so decisions and instructions have an identifiable responsibility.

Can we prepare the plan after work starts?

The plan is part of the planning process. The MRK needs to be appointed before it is filled out. Resolve the applicable submission and timing requirements before the project starts the covered activity.

Does an unchanged plan prove that nothing changed?

No. Review the demolition plan against actual conditions and records. If the scope, materials or arrangements changed, establish whether the plan needs updating and retain the assessment behind that decision.

General professional information. The individual project may require legal or technical assessment. The suggested workflows do not replace applicable requirements or competent specialist instructions.

Sources checked 9 October 2026. Technically reviewed by Kvalitetssikring Danmark ApS.

Read more in our knowledge base

New construction rules in Denmark and what your project should check

Review new construction rules in Denmark, effective dates and documentation. Check the main changes and clarify project responsibilities before work.

Read article

A contractor stop order on a Danish construction site

Understand a contractor stop order in Denmark, affected work and documentation. Check the authority process and organise follow-up before restarting.

Read article

Asbestos rules for Danish construction projects

Check asbestos rules in Denmark, company authorisation, training and documentation. Clarify the planned activity with a competent specialist before work.

Read article

Selective demolition in Denmark and the 250 square metre threshold

Understand selective demolition in Denmark, the 250 m² threshold and project roles. Check applicability, authorisation and planning before work starts.

Read article

BR18 climate requirements and the documentation your project needs

Review BR18 climate requirements, project scope and documentation. Separate building and construction-process limits and agree the calculation inputs.

Read article

A4/A5 documentation for the construction process

Organise A4/A5 documentation for transport, energy and material waste. Agree records, units and reporting responsibilities with the calculation specialist.

Read article

Discuss linked structural documentation

Keep environmental coordination with the appointed competent specialists. Where the project also has structural execution records to prepare, discuss that separate scope with KS Danmark and identify the interfaces before work begins.