Where is the information usually found? Typically in A1, A3, B1 and B2, in the document register, in descriptions and specifications and in relevant supplier and product documentation. The list is an aid to finding the information – not an indication that all documents always exist in the same form.
0 of 25 answered
  1. 1.Is the relevant structural section clearly identified?[1]
    [K/V]
  2. 2.Have interfaces with other structural sections been clarified?[1]
    [K/V]
  3. 3.Do you have the current drawings/models for the work to be carried out?[1]
    [K/V]
  4. 4.Can you identify the current revision of the design material?[2]
    [V/P]
  5. 5.Do you have the relevant descriptions, specifications and execution requirements?[1]
    [K/V]
  6. 6.Are materials/products and relevant execution requirements sufficiently defined for the work and the control to be carried out?[2]
    [V/P]
  7. 7.Is there a relevant control plan for the work?[3]
    [K]
  8. 8.Is the control type stated for the individual controls?[3]
    [K]
  9. 9.Is the control level stated?[3]
    [K]
  10. 10.Is the control scope stated?[3]
    [K]
  11. 11.Is the documentation requirement for the control stated?[3]
    [K]
  12. 12.Is the organisation/person who is to carry out the control stated?[3]
    [K]
  13. 13.Is the control plan updated to the project's current stage?[3]
    [K]
  14. 14.Is it clear what the control object/control point is?[2]
    [V]
  15. 15.Is the basis against which the control is to be carried out identifiable?[2]
    [V]
  16. 16.Is the control method sufficiently described or determined?[2]
    [V]
  17. 17.Have relevant acceptance criteria been set so that the controller can decide whether the result is accepted?[2]
    [V]
  18. 18.Has it been determined how the control is to be documented?[3]
    [K/V]
  19. 19.Has it been clarified which relevant controls are carried out as self-inspection?[2]
    [K/V]
  20. 20.Has it been clarified which controls are to be carried out independently?[4]
    [K/V]
  21. 21.Has the relevant control level/scope for the execution been determined?[5]
    [K/S]
  22. 22.If the independent control is based on documented self-inspection, has it been clarified which documentation the independent control must have access to?[3]
    [K/V]
  23. 23.Has it been clarified how identified deviations are recorded?[3]
    [K/V]
  24. 24.Has it been clarified how deviations are handled and followed up?[3]
    [K/V]
  25. 25.Is there a procedure to ensure that changed design material/revisions are used in the further execution and control?[2]
    [V/P]

Answer the last 25 questions to see the result.

Your answers are only stored in this browser until you close the tab. We do not see them unless you choose to download the report.

Sources and professional basis

  1. [1]BR18 chapter 28, §§ 494-505 – Documentation of load-bearing structures (current version), Social- og Boligstyrelsen (Danish Social and Housing Authority) bygningsreglementet.dk/Ovrige-bestemmelser/28/Krav/494_505
  2. [2]Bygningsreglementets vejledning til kapitel 30 – Kontrol af dokumentation for og udførelse af bærende konstruktioner (Guidance to the Building Regulations, chapter 30 – Control of documentation for and execution of load-bearing structures), 23.01.2025, Social- og Boligstyrelsen bygningsreglementet.dk/media/f2rp4fj1/bygningsreglementets-vejledning-til-kapitel-30-kontrol-af-dokumentation-for-og-udfoerelse-af-baerende-konstruktioner_23-01-25.pdf
  3. [3]BR18 § 523 – control, control plans, deviations, documentation and updating (current version) bygningsreglementet.dk/Ovrige-bestemmelser/30/Krav/523_528
  4. [4]BR18 Annex 3 – tables for control types and control levels (current version) bygningsreglementet.dk/bilag/b3/bilag_3/
  5. [5]BR18 Annex 3, table 2b – special control of the execution: random samples of 10 % / 25 % / 50 % in KK2 / KK3 / KK4; general control according to DS 1140 (current version) bygningsreglementet.dk/bilag/b3/bilag_3/tabel_2b/

Basis

[K]
Requirement in the current BR18
[V]
Official guidance to the Danish Building Regulations
[S]
Standard basis (DS 1140) – exact clauses are checked against the licensed standard
[P]
KS Danmark professional practice – a recommendation, not a statutory requirement

Professional basis reviewed: October 23, 2026 · Version 1.0