Kvalitetssikring Danmark ApS
Free tool

B3 Control Report Check

Is the control documentation clear and traceable?

Check whether the planned controls have been carried out, documented and can be traced to B2 and the relevant control and execution basis.

Professional basis reviewed: October 23, 2026Version 1.0Free · no registration

Please note: This tool is a professional screening. The result is not an approval, certification or project-specific liability assessment and does not replace required professional control or the work of the certified structural engineer.
B2 describes the planned control. B3 documents the control carried out.
What are you checking?
0 of 30 answered
  1. 1.Is the relevant B2 control plan available?[1]
    [K]
  2. 2.Can the B3 control records be traced to the relevant control points in B2?[1]
    [K/V]
  3. 3.Is it possible to identify which planned controls have been carried out?[2]
    [V]
  4. 4.Are any controls not carried out identified and handled?[2]
    [V]
  5. 5.Is B3 based on the relevant/current version of the control plan?[2]
    [V/P]
  6. 6.Can it be identified what has been controlled?[2]
    [V]
  7. 7.Can it be identified where the control was carried out?[2]
    [V]
  8. 8.Can it be identified when the control was carried out?[2]
    [V]
  9. 9.Can the controller be identified?[3]
    [K/V]
  10. 10.Can the relevant control basis be identified?[2]
    [V]
  11. 11.Can the relevant drawing/document revision be identified where necessary for traceability?[4]
    [V/P]
  12. 12.Is the result of the control carried out stated?[2]
    [V]
  13. 13.Can the result be assessed against the relevant control basis/acceptance criterion?[2]
    [V]
  14. 14.Has the required form of documentation been used?[3]
    [K/V]
  15. 15.Is the control scope documented sufficiently to show what the control actually covered?[3]
    [K/V]
  16. 16.Are relevant attachments/photos/measurements unambiguously linked to the control record?[2]
    [V/P]
  17. 17.Have the deviations found been identified?[3]
    [K]
  18. 18.Are the deviations described sufficiently for the matter to be understood?[2]
    [V]
  19. 19.Have the deviations been handled?[3]
    [K]
  20. 20.Are relevant corrective actions documented?[2]
    [V]
  21. 21.Has the necessary follow-up control been carried out and documented?[2]
    [V]
  22. 22.Is it possible to see whether the deviation has been completed/closed?[4]
    [V/P]
  23. 23.Is it clear which records relate to self-inspection and which relate to independent control?[5]
    [K/V]
  24. 24.Has the relevant independent control been carried out and documented?[5]
    [K]
  25. 25.If the independent control is based on documented self-inspection, is the necessary self-inspection documentation available and traceable?[3]
    [K]
  26. 26.Can the result of the independent control be traced to the relevant control points/the control basis?[2]
    [K/V]
  27. 27.Are all relevant control areas from B2 either documented or explained?[1]
    [K/V]
  28. 28.Are relevant deviations closed or clearly marked as outstanding?[3]
    [K/V]
  29. 29.Are the control report and attachments organised so that the control can be verified?[2]
    [V]
  30. 30.Is the documentation ready to form part of the complete structural documentation?[6]
    [K/V]

Answer the last 30 questions to see the result.

Your answers are only stored in this browser until you close the tab. We do not see them unless you choose to download the report.

Sources and professional basis

  1. [1]BR18 § 502 – the structure of the structural documentation, including A4, A5, B2 and B3 (current version) bygningsreglementet.dk/Ovrige-bestemmelser/28/Krav/494_505
  2. [2]Bygningsreglementets vejledning til kapitel 30 – Kontrol af dokumentation for og udførelse af bærende konstruktioner (Guidance to the Building Regulations, chapter 30 – Control of documentation for and execution of load-bearing structures), 23.01.2025, Social- og Boligstyrelsen bygningsreglementet.dk/media/f2rp4fj1/bygningsreglementets-vejledning-til-kapitel-30-kontrol-af-dokumentation-for-og-udfoerelse-af-baerende-konstruktioner_23-01-25.pdf
  3. [3]BR18 § 523 – control, control plans, deviations, documentation and updating (current version) bygningsreglementet.dk/Ovrige-bestemmelser/30/Krav/523_528
  4. [4]KS Danmark professional practice. The item is not a separate statutory requirement; it supports traceability, usability or practical execution of the control.
  5. [5]BR18 Annex 3 – tables for control types and control levels (current version) bygningsreglementet.dk/bilag/b3/bilag_3/
  6. [6]BR18 chapter 28, §§ 494-505 – Documentation of load-bearing structures (current version), Social- og Boligstyrelsen (Danish Social and Housing Authority) bygningsreglementet.dk/Ovrige-bestemmelser/28/Krav/494_505

Basis

[K]
Requirement in the current BR18
[V]
Official guidance to the Danish Building Regulations
[S]
Standard basis (DS 1140) – exact clauses are checked against the licensed standard
[P]
KS Danmark professional practice – a recommendation, not a statutory requirement

Professional basis reviewed: October 23, 2026 · Version 1.0